बेबाक · Editorial ⚖️ Reform India
CAG flags ₹33.19 crore in irregular CAPF allowances, stalled projects
The government's own auditor found ₹33.19 crore in Risk and Hardship Allowance paid in ineligible areas, plus a CISF flats project whose cost ballooned 103% while still incomplete.
What the auditor found
The Comptroller and Auditor General of India's compliance audit for the year ended March 2023 (Report No. 22 of 2025) is not a political document—it is the state auditing itself. Across civil and commercial ministries, it catalogues money spent without the intended result: allowances paid where they were not due, buildings that sit empty, and construction costs that swelled far beyond the contract. Each figure below is drawn from that report. Read together, they describe not scandal but drift—rules on paper that were not enforced in practice, and public funds that produced neither service nor asset.
Allowances paid where they were not due
The single largest item is the Risk and Hardship Allowance in the Central Armed Police Forces. The Ministry's office memorandum of 22 February 2019 tied the allowance to classified areas. The audit found the payment could not be regulated accordingly, resulting in irregular payment of ₹33.19 crore between March 2020 and March 2023. The named instances are concrete: RHA was paid to CISF units at Guwahati and Dibrugarh Airport and to 68 Bn SSB units in Assam locations not classified as eligible. This is not a dispute over whether personnel face hardship—it is a failure to apply the government's own eligibility map to its own payroll.
Flats that money could not finish
At Maidangarhi in Delhi, residential flats for CISF personnel show how planning gaps compound into cost. NBCC submitted a revised memorandum-of-understanding cost of ₹56.15 crore—approximately 103 per cent over the awarded cost of ₹27.56 crore—while the work remained incomplete. The audit attributes the escalation to defective planning, and records that ₹11.75 crore of funds was blocked with the intended outcome, residential accommodation, not achieved. The government may fairly note that construction estimates evolve; but a doubling of cost on an unfinished building is precisely the kind of outcome the audit exists to surface.
Assets built or bought, then left idle
Two entries show capital converted into idle expenditure. A site acquired at Karera in Madhya Pradesh in August 2017 for ₹16.55 crore—land taken for thirty years—could not be put to use, producing idle expenditure of ₹17.44 crore. Separately, ₹14.57 crore spent on constructing an ITBP building remained idle because the building was not put to use for more than four years. These are not accounting abstractions: they are a completed structure and a paid-for site that delivered no operational benefit while the money was committed and gone.
Smaller leaks, same pattern
The report's lesser figures repeat the theme of avoidable outflow. Regional Passport Offices under the Ministry of External Affairs made incorrect GST payments of ₹2.96 crore from July 2017 to June 2022. The National Gallery of Modern Art, under the Ministry of Culture, paid ₹1.97 crore in avoidable fixed electricity charges because its sanctioned load was not revised to a realistic level. On ex-gratia payments, the CISF had recovered ₹2.95 crore from the concerned PSUs as of January 2024, but ₹1.10 crore remained outstanding. Individually modest, together they point to controls that catch problems late, if at all.
The case for reform
The verdict is reform, not indictment. Every rupee cited here comes from the government's own auditor, and several entries—the CISF recovery of ₹2.95 crore, for instance—show the system can claw money back once errors are found. What the report exposes is the gap between rule and execution: eligibility memoranda not applied, load sanctions not revised, sites and buildings commissioned without a path to use. The fixes are procedural, not partisan—tighter linkage of payments to sanctioned entitlements, realistic utility contracting, and a use-before-you-build discipline on capital projects. The data desk's ask is simple: enforce the rules already on the books.
A revised cost of ₹56.15 crore—103 per cent over the awarded ₹27.56 crore—and the flats still stand unfinished.
What this editorial rests on
Drawn from our live multi-newsroom feed — read the reporting at source.
An editorial is the considered opinion of The Mudda desk, argued from the sourced reporting above and written under our published persona, बेबाक. We name institutions, not parties. If we are wrong, we will say so. How we work →