Chhattisgarh's Jal Jeevan Mission: a third of taps run dry by the CAG's own audit

Of 40.10 lakh household tap connections installed under the Jal Jeevan Mission in Chhattisgarh, 13.31 lakh (33 per cent) were non-functional as of January 2025, the Comptroller & Auditor General found in its audit for the period ended March

बेबाक · The Mudda Editorial Desk
A neat row of shiny brass taps fixed to a village wall in a dusty courtyard, each dry, with a single cracked clay pot waiting beneath, and a distant woman's silhouette carrying water from far away.
Illustration generated with AI for The Mudda

A third of the taps do not work

The promise of the Jal Jeevan Mission is simple: a working tap in every rural home. The CAG's performance audit for the period ended March 2024 measures Chhattisgarh against that promise using the government's own records. Out of 40.10 lakh Functional Household Tap Connections (FHTCs) installed, 13.31 lakh — 33 per cent — were non-functional as of January 2025. The audit attributes this to dry sources, incomplete overhead tanks, absent electric connections and un-installed solar pumps. These are not connections that were never built; they are connections that were counted, paid for, and yet deliver no water. A tap that does not run is, for the household behind it, indistinguishable from no tap at all.

The certification gap

The mission's own yardstick for success is 'Har Ghar Jal' village certification — the point at which a village confirms every home has an assured supply. The target was 100 per cent certification of 19,656 villages. As of March 2024, only 716 villages — 3.64 per cent — had been certified. The distance between the target and the achievement is not a rounding error; it is the difference between a mission substantially delivered and one barely begun. The audit does not dispute that connections were installed at scale. It documents, rather, that installation and assured, verified service are two very different milestones, and that Chhattisgarh has reached far more of the first than the second.

Money that never arrived, and money that overpaid

The audit traces two financial failures. First, because the mission was slow to initialise in its first two years, the State Mission could not mobilise ₹6,480.04 crore from the Centre (₹3,285.38 crore) and the State's own contribution (₹3,194.66 crore) — funds a faster start could have drawn down. Second, on the spending side, with 34.29 lakh FHTCs installed in the state by March 2024, the audit finds a probability of excess payment up to ₹533.668 crore arising from incorrect rate analysis of the FHTC. In 22 test-checked Single Village Schemes, payment was made to the contractor at a flat unit rate of ₹6,969 per FHTC without item-wise detailed measurement. The Government has intimated that a deduction of ₹53.25 crore was recovered from 1,915 agreements across districts.

Who pays for the premium

Tendering added costs the Centre will not share. The sanctioned cost of 11,055 schemes was revised from ₹7,840.94 crore to ₹8,366.58 crore on account of tender premium — a difference of ₹525.64 crore that, the audit notes, will not be borne by the Central Government and falls to the State. The pattern repeats within the Single Village Schemes: for 7,629 such schemes, the original administrative sanction of ₹6,622.91 crore was revised to ₹7,056.28 crore, a difference of ₹433.37 crore to be carried by the State exchequer. However the individual tenders are justified, the cumulative effect is a growing bill settled from state funds rather than shared central support.

The parts of the mission that got starved

Two functions meant to keep the water safe and the community involved were under-resourced. Expenditure on Water Quality Monitoring and surveillance was ₹40.88 crore against a provisioned two per cent amount of ₹199.79 crore — a fraction of what was set aside to ensure the water reaching homes is fit to drink. Support activities, which build the local capacity to run and maintain schemes, fared similarly: against ₹499.47 crore mandated over 2019-20 to 2023-24, only ₹216.07 crore was allocated. Engineering hardware without water-quality assurance and community readiness is precisely how functional taps become non-functional ones.

Built, but not handed over

The scale of incompletion is starkest in the handover data. Of 29,153 Single Village Schemes and 70 Multi Village Schemes sanctioned, only 172 Single Village Schemes had been completed as of March 2024 — and of those, just 32 had been handed over to the community or Gram Panchayat. Completion and handover are what convert construction into a durable public service a village actually owns and maintains. The audit also documents that solar photo-voltaic based water schemes failed to meet the prescribed minimum service level for 28,984 households, because FHTC connections were loaded beyond the capacity of the installed solar systems. The reform the CAG's figures point to is not more announcements, but functional delivery, verified quality, and completed handovers — measured on the government's own scale.

The state built 40.10 lakh taps but 13.31 lakh of them do not deliver water, and only 716 of 19,656 villages could be certified 'Har Ghar Jal'.
governanceauditpublic-healthinfrastructurefinance

What this editorial rests on

Drawn from our live multi-newsroom feed — read the reporting at source.